Chennai Metro Phase II: 82 Per Cent Land Acquisition Complete, Size Of Metro Stations Pruned To Expedite Acquisition

  • The estimated cost of the Phase II project is‌‌ Rs 63,246 crore. Construction is expected to be completed by the end of 2026.

V Bhagya SubhashiniJan 30, 2023, 11:01 AM | Updated Feb 02, 2023, 07:20 AM IST
Chennai Metro Rail. (Representative Image)

Chennai Metro Rail. (Representative Image)


The land acquisition for Chennai Phase II of the Metro Rail project is almost complete.

About 82 per cent of the required land has been acquired so far, according to Chennai Metro Rail Ltd (CMRL).

The expansion of Metro Phase II is planned with a network length of 118.9 km with 128 stations. It consists of three corridors, namely Corridor-3 from Madhavaram to SIPCOT (45.8 km), Corridor-4 from Lighthouse to Poonamalle Bypass (26.1 km), Corridor-5 from Madhavaram at Sholinganallur (47 km).

According to CMRL officials, 93 hectares of the 112.72 hectares needed for the project have been acquired.


According to the CMRL authorities, measures were taken to make land acquisition for the Phase II project simple and swift. 

For instance, compared to the Phase I project, the size of the stations of Phase II has been reduced significantly. The size of stations was lessened from 220 meters in Phase I to 150 meters in Phase II.

Similarly, each station will only have two entry and departure ports in Phase II as opposed to four in each station in Phase I.

Map of Chennai Metro Rail Project Phase - II (CMRL)

Currently, the Chennai Metro Rail is pushing up its efforts to open the section between Poonamallee and Light House to the public within three years.

The estimated cost of the Phase II project is‌‌ Rs 63,246 crore. Construction is expected to be completed by the end of 2026.


There are 41 stations of which 21 are underground and 20 elevated. The entire Phase-I is fully operational.