Haryana Government Approves Delhi-Panipat And Delhi-Gurugram-Alwar RRTS Projects

Amit MishraMay 16, 2023, 11:51 AM | Updated 11:59 AM IST
The NCRTC announced and unveiled the logo of the RAPIDX on 11 April.

The NCRTC announced and unveiled the logo of the RAPIDX on 11 April.


The Haryana government on Monday (15 May) gave its approval to the Delhi-Gurugram-Shahjahanpur-Neemrana-Behror-Alwar and Delhi-Panipat Regional Rapid Transit System (RRTS) projects.

The approval came during the RRTS meeting chaired by chief secretary Sanjeev Kaushal in Chandigarh on 16 May.

Delhi-SNB Project


The length of the corridor passing through Delhi, Haryana, and Rajasthan are 23 km, 83 km, and 2 km, respectively.

The proposed stations on the Delhi-SNB corridor include Sarai Kale Khan, INA, Munirka, Aerocity, Udyog Vihar, Sector-17, Rajiv Chowk, Kherki Daula, Manesar, Panchgaon, Bilaspur Chowk, Dharuhera, MBIR, Rewari, Bawal and SNB.

The 107-km-long Delhi-SNB RRTS corridor is part of the Delhi-Arwal RRTS line. One of the three RRTS corridors prioritised for implementation, Delhi-Gurugram-Alwar is planned to be implemented in three stages.

Delhi-Alwar RRTS Alignment


Alignment OF SKK-SNB RRTS Corridor

The line would be extended from SNB Urban Complex  to Sotanala (33.3 km), with Shahjahanpur, Neemrana, and Behror in between, under the second phase. SNB to Alwar (58 km) extension is proposed under the third phase.

This corridor will be interoperable with the Delhi-Ghaziabad-Meerut RRTS corridor, facilitating commuters to travel between one corridor to another without the need to change the train.

Similarly, with an intent to incentivise the use of Public Transport, RRTS stations on this corridor will be seamlessly integrated with other modes of transport  — Metro rail, railway station and ISBT at Sarai Kale Khan; Metro rail at INA, Aerocity, Udyog Vihar in Gurgaon, Kherki Duala, and Panchgaon and IGI airport at Aerocity.

The corridor is planned to be constructed in about five years’ time, excluding one year of pre-construction activities at a base construction cost of Rs 37,987 crore, funded by government of India (20 per cent), concerned state governments (20 per cent) and bilateral/multilateral funding agencies (60 per cent).


In a big boost to the project, the Centre in Feb 2023 included the Delhi-Gurugram-SNB corridor under the ambit of PM Gati Shakti masterplan — this is likely to result in faster approvals and expeditious completion of the much-delayed project.

Delhi-Panipat RRTS Corridor

The Delhi-Panipat RRTS corridor of 103-km-long alignment would have an elevated length of 11.5 km and 91.5 km underground.

Delhi-Panipat RRTS Corridor

It would have two underground, 14 elevated, and two at-grade stations. Two depots have been planned at Murthal and Panipat. The length passing through Delhi and Haryana are 36.2 km and 66.8 km, respectively.

RRTS


In the first phase of the project, three corridors, namely, Delhi-Ghaziabad-Meerut, Delhi-SNB-Alwar and Delhi-Panipat are under implementation.

RRTS Phase-I Map

In the next phase(s), five additional RAPIDX lines will be developed.


RRTS Route Map

The National Capital Region Transport Corporation (NCRTC), which works under the administrative control of Ministry of Housing and Urban Affairs (MoHUA) and is executing the RRTS project is a joint venture of the Government of India (50 per cent) and state governments of Haryana (12.5 per cent), NCT Delhi (12.5 per cent), Uttar Pradesh (12.5 per cent) and Rajasthan (12.5 per cent).