Himachal Pradesh: BHEL Completes Modernisation Of 40 Year Old Baira Siul Hydro Power Station

India InfrahubOct 21, 2021, 04:30 PM | Updated 04:30 PM IST
Baira Siul Power Station (NHPC Limited)

Baira Siul Power Station (NHPC Limited)


Bharat Heavy Electricals Limited (BHEL) has completed Renovation and Modernisation (R&M) and commissioned the third and final unit of the 3x60 MW Baira Siul Hydro Power Station located in Chamba district of Himachal Pradesh.

The first and second units of the station have already been renovated and commissioned in Dec 2019 and Oct 2020, respectively.

BHEL had won the order for R&M of the three units of Baira Siul Hydro Power Station amidst stiff competitive bidding.

Set up in 1981, Baira Siul is the first hydro station of NHPC Limited and the first to be taken up for comprehensive Renovation and Modernisation (R&M).


Notably, BHEL is also the Original Equipment Manufacturer (OEM) of the hydro units, which have been successfully operating for over 35 years before being taken up for comprehensive R&M.

BHEL's scope in the project comprised design, manufacture, supply, replacement and commissioning of critical parts of Turbines and auxiliaries, Governors, Generators and Control and Monitoring.

The equipment has been supplied from BHEL's manufacturing units at Bhopal, Bengaluru and Jhansi, while the on-site installation activities were carried out by the company's Northern Region division, Noida.

Currently, BHEL is carrying out comprehensive R&M of 14 hydro sets across the country, aggregating to 639 MW.