Prime Minister Narendra Modi and his Japanese counterpart Shinzo Abe shake hands in front of a shinkansen train during their inspection at a bullet train manufacturing plant in Kobe, Hyogo prefecture on 12 November 2016. (JIJI PRESS/AFP/Getty Images)
Railway Board Chairman Vinod Kumar Yadav has stated that the time frame for the completion of the bullet train project can be determined in the upcoming three-six months, Press Trust of India has reported.
The major reason behind this is that only 23 per cent of land has been acquired in Maharashtra so far for the initiative in comparison to the 82 per cent of land that has been obtained in Gujarat. Apparently, the COVID-19 pandemic has caused a postponement in the whole process, though Yadav believed that they are progressing well as of now.
Yadav mentioned that work can commence only after a certain amount of land has been procured in a linear project like for the bullet train. He asserted that the bidding procedure can initiate in the upcoming few months.
The top officer clarified, “As the COVID19 situation improves, we will be able to start the bidding process and within the next three to six months, we will be able to get the status of land acquired and then we will be able to provide a real time frame for the completion of the project.”